2022 | Upgrade of Iron Gate 2 Navigation Lock | Đerdap 2 |
2020 | Production and installation of cooling system of HPP ĐERDAP 1 | Đerdap 1 |
2020 | Fabrication and installation of pipe system of turbine regulation of HPP ĐERDAP 1 | Đerdap 1 |
2019 | Capital overhaul BPZ A2 at HE ĐERDAP 2 | Đerdap 2 |
2018 | Capital overhaul BPZ A7 and radial gate overhaul at HE ĐERDAP 2 | Đerdap 2 |
2017 | Works on production and delivery of cooling system for the aggregate phase V of revitalization | Đerdap 2 |
2016 | Fabrication and installation of piping systems for the aggregate Phase V of turbine regulation revitalization | Đerdap 2 |
2014 | Manufacture & installation of turbine regulation pipeline A-5 | Đerdap 2 |
2014 | Manufacture & delivery of pipeline of cooling system A-5 | Đerdap 2 |
2013 | Capital overhaul BPZ A8 and HMO electric and overflow dam HPP Đerdap 2 | Đerdap 2 |
2012 | Capital overhaul of HMO channel locks A-6 HE ĐERDAP 2 | Đerdap 2 |
2011 | Capital overhaul of BPZ A9 | Đerdap 2 |
2010 | Capital overhaul of BPZ A4 | Đerdap 2 |
Goša Montaža operates through an Integrated Management System consisting of ISO 9001 Quality Management System, ISO 14001 Environmental Management System and ISO 45001 Occupational Health and Safety Management System.
The complete process from design to erection is in accordance with EN 1090-2, and welding works are according to EN ISO 3834-2.
Knićaninova 3, Belgrade, Serbia
Head office: +381 11 303.58.33
Management: +381 26 317.126
montaza@gosamontaza.rs
www.gosamontaza.rs
Copyright © GOŠA Montaža • Web by Agencija Kraguljac